The following section presents the
information relating the various phases of manufacturing of the fixture.
Purchase of raw material:
The team select steel 1045 as
material, the brand name of steel 1045 is (C 45). The team bought steel 1045 as
plate (100cm*100cm) from Ateyah Company.
Metal Cutting:
The team did cutting as Ox fuel
Cutting (OFC). The Ox fuel Cutting (OFC)
is more and common and available in workshops.
Welding:
Joining process in which two (or
more) parts are coalesced at their contacting surfaces by application of heat
and/or pressure. The team did the arc welding as type of welding.
Grinding:
The team did the grinding to remove
the sharp edge and to be more safety to use, and get good surface finish.
Cleaning and painting:
The team did the painting to get better
texture. The team try to select same colour of lathe machine in the lap to be good
looking when the fixture fixed on machine.
No comments: